Construction Update: 11/9/18

November 9, 2018

Crews will be conducting nightwork on Palos Verdes Drive North, from Dapplegray Elementary School to Palos Verdes Drive East, starting the week of November 12 to complete minor finishing work and reduce the number of plates in the area. Work is expected to take place from Monday to Friday, 10 p.m. to 5 a.m., and at least one lane of traffic will be open in each direction at all times.

Construction on Palos Verdes Drive North, between Dapplegray Lane and Montecillo Drive, is expected to continue from Monday to Friday, between 9 a.m. and 7 p.m. There will be at least one lane of traffic open in each direction at all times, with lanes reopening after work hours.

Crews will be working on Montecillo Drive, between Encanto Drive and Palos Verdes Drive North, and will involve potholing and utility line surveying. Work is ongoing from Monday to Friday, between 7 a.m. and 5 p.m. There will be at least one lane of traffic open in each direction at all times, with lanes reopening after work hours.

Work in the Dapplegray Elementary School access road, which leads to the Rolling Hills Little League ballfield, continues from Monday to Friday, 7 a.m. to 5 p.m. We are working closely with the Rolling Hills Little League and Dapplegray Elementary School to coordinate all necessary details as the access road remains closed for construction.

Construction for the new pump station on Crenshaw Boulevard, north of Silver Spur Road, is projected to begin in mid-November and continue through the end of 2019. In the coming weeks, residents will start to see crews clearing the area around the location as part of preparatory work.

A reminder that the Palomino Ranchos Bridle Trail, between the ballfield and Rolling Hills Road, remains closed to the public as work continues in the trail. For a map of anticipated trail closures and route detours, visit the equestrian page

Please note that the construction dates provided are estimates, not exact deadlines, and the actual duration of night work may change based on a number of factors, including unknowable field circumstances. For the latest project information, please refer to the updated timeline on our Map & Timeline page.