Construction Update: 12/20/18

December 20, 2018

Nightwork is ongoing on Palos Verdes Drive North, between Dapplegray Elementary School and Palos Verdes Drive East, which includes the removal of steel plates in the area and other finishing work. Work will occur from Monday to Friday, 10 p.m. to 5 a.m. until late January 2019. During this time, vehicles will be able to travel in each direction at all times.

Crews are conducting minor finishing work on Palos Verdes Drive North, between Montecillo Drive and Palos Verdes Drive East, from Monday to Friday, 9 a.m. to 7 p.m. At least one lane of traffic will be open in each direction at all times, with lanes reopening after work hours.

Landscape restoration, in addition to other finishing work, is now underway on Montecillo Drive, between Encanto Drive and Palos Verdes Drive North, and is expected to occur from Monday to Friday, between 7 a.m. and 5 p.m. Final paving of the area is expected to be complete by early next year. We are working closely with the Montecillo Homeowners’ Association to coordinate all necessary details.

Work continues near the Rolling Hills Little League ballfield as well as in the Palomino Ranchos Bridle Trail, between the ballfield and Rolling Hills Road. A reminder that the Dapplegray Elementary School access road and Palomino Ranchos Bridle Trail remain closed to the public as work is ongoing. For a map of ongoing trail closures and route detours, visit our equestrian page.

Nightwork has begun in the parking lot of the Rolling Hills United Methodist Church, along the Botanic Garden property near Crenshaw Boulevard, and will continue from Monday to Friday, between 7:30 p.m. and 5:30 a.m. The parking lot will be accessible during non-work hours.

Work will soon begin on the Botanic Garden Trail, between Rolling Hills Road and Crenshaw Boulevard, from Monday to Friday, between 7 a.m. and 5 p.m. The Botanic Garden Trail will be closed to pedestrians and riders until spring 2019. Riders are encouraged to avoid the work area due to construction-related noise that may startle a horse.

Preparatory work continues for the new pump station on Crenshaw Boulevard, which is expected to be complete by the end of 2019. Residents should expect to see deliveries of materials to the pump station site as well as other work needed to prepare for construction.

For the latest timeline information, please refer to the updated timeline on our Map & Timeline page. Please note that the construction dates provided are estimates, not exact deadlines, and the actual duration of night work may change based on a number of factors, including unknowable field circumstances and weather.