Construction Update: 12/5/18

December 5, 2018

Nightwork is ongoing on Palos Verdes Drive North, between Dapplegray Lane and Palos Verdes Drive East, as crews continue to remove steel plates in the area and complete other minor finishing work. Work will occur from Monday to Friday, 10 p.m. to 5 a.m. until approximately the end of January. During this work, vehicles will be able to travel in each direction at all times.

Crews will be conducting minor finishing work on Montecillo Drive, between Encanto Drive and Palos Verdes Drive Northbetween 7 a.m. to 5 p.m. and on Palos Verdes Drive North, between Montecillo Drive and Palos Verdes Drive East, between 9 a.m. to 7 p.m. Final paving of the area is expected to be completed by early next year. We are working closely with the Montecillo Homeowners’ Association to coordinate all necessary details.

Work is ongoing near the Rolling Hills Little League ballfield as well as in the Palomino Ranchos Bridle Trail, between the ballfield and Rolling Hills Road. A reminder that the Dapplegray Elementary School access road and Palomino Ranchos Bridle Trail remain closed to the public as work continues. For a map of anticipated trail closures and route alternatives, visit our equestrian page

Crews are expected to begin work on the Botanic Garden Trail and Botanic Garden Property starting next week. Work is expected to take place from Monday to Friday, between 7 a.m. and 5 p.m. The Botanic Garden Trail, from Rolling Hills Road to Blossom’s Trail, will be closed to pedestrians and riders until spring 2019. Residents on Lariat Lane will see pipe deliveries as work commences and we encourage riders to avoid the work area due to work-related noise that may startle a horse.

Preparation for construction of the new pump station on Crenshaw Boulevard is underway, and construction is expected to continue through the end of 2019. Residents will start to see deliveries of materials and other activities to help prepare the area around the pump station site.

For the latest timeline information, please refer to the updated timeline on our Map & Timeline page. Please note that the construction dates provided are estimates, not exact deadlines, and the actual duration of night work may change based on a number of factors, including unknowable field circumstances.