REMINDER: Please obey all posted road/trail closure signage and traffic control personnel while navigating work zones. For your safety and that of crews, please refrain from moving any traffic cones in construction areas. Thank you!

Crews are conducting cleaning and grouting of the new pipeline at the Dapplegray Elementary School property from Monday to Friday, 7 a.m. to 5 p.m.

Pipeline installation continues along the Palomino Ranchos Bridle Trail, moving east towards the Little League ballfield. Work in this area will occur from Monday to Friday, between 7 a.m. and 5 p.m. During this time, the trail will be closed to the public and we encourage riders to avoid the area due to construction-related noise that could startle a horse. As work is ongoing, the Dapplegray Elementary School access road will remain closed to the public from Monday to Friday until 3:30 p.m., at which point parents will be able to use the road for little league practices.

Work is ongoing on the Botanic Garden property, between Crenshaw Boulevard and Rolling Hills Road. Work hours are from Monday to Friday, 7 a.m. to 5 p.m. For the safety of equestrians and crews, the Botanic Garden Trail, from Blossom’s Trail to Rolling Hills Road, will remain closed while work is underway on the property and trail.

Construction continues at the new pump station site on Crenshaw Boulevard, north of Silver Spur Road, from Monday to Friday, between 7 a.m. and 5 p.m. During work hours, there will be traffic control on Crenshaw Boulevard and at least one lane of traffic will be open in each direction at all times.

Please refer to the project timeline on our Map & Timeline page for the latest construction information. As a reminder, all the construction dates outlined in the timeline are estimates and the length of work can change based on several factors, including inclement weather and unknowable field circumstances.