Construction Update: August 2019

August 2019

Pipeline delivery and installation are in progress along Crenshaw Boulevard near Crest Road. Crews will continue to install pipeline down Crenshaw Boulevard, moving north toward Silver Spur Road, from Monday to Friday, between 9 a.m. and 7 p.m. Parents, Teachers, and Faculty: As school resumes, please plan for construction-related traffic delays and use alternate routes where possible. As a reminder, use Google Maps, Apple Maps, or Waze for real-time traffic information.

Crews are continuing construction work at the new pump station site on Crenshaw Boulevard, north of Silver Spur Road. This work is taking place from Monday to Friday, between 7 a.m. and 5 p.m. Traffic control will be in place during work hours and at least one lane of traffic will be open in each direction at all times.

Pipeline installation is underway in the South Coast Botanic Garden property, between Crenshaw Boulevard and the end of Lariat Lane. Crews are working from Monday to Friday, between 7 a.m. and 5 p.m. The Botanic Garden Trail, from Blossom’s Trail to Rolling Hills Road, will remain closed for the safety of residents and crews.

As a reminder, the Palomino Ranchos Bridle Trail, between Rolling Hills Road and the Rolling Hills Little League ballfield has reopened. We appreciate your patience during the closure and hope you enjoy a summer ride in celebration!

Restoration work is ongoing in the parking lot of Dapplegray Elementary School. This work is taking place from Monday to Friday, between 7 a.m. and 5 p.m., and should be completed prior to the start of school.

Please visit our Map & Timeline page for more detailed information and follow us on Facebook for updates. Please note that all provided construction dates are estimates, rather than exact deadlines, and may change based on many factors, such as unforeseeable field circumstances.