Construction Update: September 2019

September 2019

Crenshaw Boulevard Work

Crews continue to install pipeline down Crenshaw Boulevard, moving from Crest Road toward Silver Spur Road, from Monday to Friday, between 9 a.m. and 7 p.m.Pipeline installation is currently underway in the intersection of Crenshaw Boulevard and Crestridge Road.

In upcoming weeks, crews will repave Crenshaw Boulevard from Crest Road to Crestridge Road, removing several steel plates.

From there, pipeline installation will take place in the intersection of Crenshaw Boulevard and Indian Peak Road. Please see below for a graphic depicting anticipated traffic control measures for this stage of work.

There will be at least one lane of traffic open in each direction at all times. All traffic control will be removed and flashing traffic lights will return to normal at the end of each workday. Please expect delays while work takes place and use alternate routes where possible.

Other Work

Work continues at the new pump station site on Crenshaw Boulevard, north of Silver Spur Road, from Monday to Friday, between 7 a.m. and 5 p.m. Traffic control is in place during work hours and at least one lane of traffic will be open in each direction at all times.

Pipeline installation is ongoing in the South Coast Botanic Garden property, between Crenshaw Boulevard and the end of Lariat Lane. Crews are working from Monday to Friday, between 7 a.m. and 5 p.m. For the safety of residents and crews, the Botanic Garden Trail, from Blossom’s Trail to Rolling Hills Road, will remain closed until work is complete.

For more information, please visit the Map & Timeline page on our website and follow us on Facebook for updates. As a reminder, all construction timing is estimated and could change based on several factors, including unforeseeable field circumstances.